Capital Investment and Project Information (January 2010 to date)
|
Status | Year Completed | Project Complete Cost | Description |
Complete
|
2011
|
$18,301.63
|
Swimming Pool Renovation
|
In Progress
|
|
$1,055,986.12
|
ADA Renovation, Bathrooms, Ceiling, Concrete, Demolition, Doors, Environmental, Finishes, Fixtures, Hardware, Industrial Hygiene, Interior / Exterior Signage, Interior Renovation, Lighting, Lockers, Mechanical, Painting, Partitions, Plumbing, Pool, Pool Deck
|
In Progress
|
|
$1,923,229.62
|
Structural Renovation
|
In Progress
|
|
$10,455,962.43
|
Exterior Renovation
|
In Progress
|
|
$14,701,239.48
|
ADA Improvements
|
|
|
Lease Information
|
Download Lease | Description | Lease/Lic. Type | Lessor/ Licensor | Lessee/ Licensee | Lease Detail |
|
Health services
|
License
|
CPS
|
Youth Guidance
|
View
|
|
|