Capital Investment and Project Information (January 2010 to date)
|
Status | Year Completed | Project Complete Cost | Description |
Complete
|
2011
|
$1,568,061.27
|
ADA Renovation, Bathrooms, Demolition, Doors, Elevators, Finishes, Fire Alarms, Interior Renovation, Painting
|
Complete
|
2011
|
$875,518.09
|
Boiler/Mechanical System Renovation
|
Complete
|
2010
|
$4,349,088.00
|
ACM Abatement, ADA Renovation, Air Conditioning, Asphalt, Bathrooms, Boilers, Campus Park, Carpeting, Caulking, Ceiling, Concrete, Construction Inspection and testing, Demolition, Doors, Electrical, Entrance Door, Environmental, Exterior Construction, Fencing
|
|
|